About this Project
Degnan approached HRC Security for the SYD09 Data Centre development based on our expertise in data centre and critical infrastructure security. The project involved securing four substation kiosks with 4.5-metre-high 358 welded mesh fencing and controlled pedestrian access gates, delivering a robust anti-climb, anti-cut perimeter solution for authorised personnel access.
Project Scope
Key works completed as part of the project included:
- Supply and installation of 4.5m high 358 welded mesh security fencing
- Construction of secure perimeter enclosures for four substation kiosks
- Supply and installation of pedestrian access gates
- Integration of access points to support authorised personnel access
- Delivery of security infrastructure in accordance with project and site requirements
Outcome
HRC Security delivered a robust, low-maintenance perimeter security solution that protects critical electrical infrastructure and provides secure, controlled access within the SYD09 Data Centre development.
RELATED Projects
PROTECTING CRITICAL INFRASTRUCTURE
HRC implemented a system involving multiple technologies and layers of security.
ADVANCED SECURITY SYSTEM FOR AUTOCARE
High-tech security systems that protect the employees and saved thousands of dollars.
Security system upgrade at Dillwynia Jail
High-end, multi-zone, dual-layered perimeter security system.